Author:Talo, Antti
Title:Rakentamisen tuottavuusmittaus laatu- ja aikataulutekijöillä
Construction productivity measurement via schedule and quality factors
Publication type:Master's thesis
Publication year:2011
Pages:(5) + 71 s. + liitt. 7      Language:   fin
Department/School:Rakennustekniikan laitos
Main subject:Rakentamistalous   (Rak-63)
Supervisor:Saari, Arto
Instructor:Romo, Ilkka ; Junnonen, Juha-Matti
OEVS:
Electronic archive copy is available via Aalto Thesis Database.
Instructions

Reading digital theses in the closed network of the Aalto University Harald Herlin Learning Centre

In the closed network of Learning Centre you can read digital and digitized theses not available in the open network.

The Learning Centre contact details and opening hours: https://learningcentre.aalto.fi/en/harald-herlin-learning-centre/

You can read theses on the Learning Centre customer computers, which are available on all floors.

Logging on to the customer computers

  • Aalto University staff members log on to the customer computer using the Aalto username and password.
  • Other customers log on using a shared username and password.

Opening a thesis

  • On the desktop of the customer computers, you will find an icon titled:

    Aalto Thesis Database

  • Click on the icon to search for and open the thesis you are looking for from Aaltodoc database. You can find the thesis file by clicking the link on the OEV or OEVS field.

Reading the thesis

  • You can either print the thesis or read it on the customer computer screen.
  • You cannot save the thesis file on a flash drive or email it.
  • You cannot copy text or images from the file.
  • You cannot edit the file.

Printing the thesis

  • You can print the thesis for your personal study or research use.
  • Aalto University students and staff members may print black-and-white prints on the PrintingPoint devices when using the computer with personal Aalto username and password. Color printing is possible using the printer u90203-psc3, which is located near the customer service. Color printing is subject to a charge to Aalto University students and staff members.
  • Other customers can use the printer u90203-psc3. All printing is subject to a charge to non-University members.
Location:P1 Ark Aalto  8986   | Archive
Keywords:construction
productivity
quality
schedules
performance measurement
rakentaminen
tuottavuus
laatu
aikataulut
suorituskykymittarit
Abstract (eng): Productivity is an important indicator at both the corporate and national economy level and it has a direct connection to profitability.
Traditionally productivity is seen as output and input relationship of some process and productivity can be improved by developing this relationship.
The development of productivity, decision-making and control activities can be supported with productivity measurement.
Construction industry's diversity and uniqueness makes it challenging for the productivity measurement.
For this reason productivity should be approached through different kind of performance indicators.

The topic of this master's thesis was an indirect measure of productivity via quality and schedule factors.
The aim was to clarify the definition of productivity in the construction industry, to find out the schedule and quality factors impact on productivity as well as identify and evaluate the performance measures for time and quality factors.
In addition the aim was to determine the selection criteria for the performance measure indicators.
The target company of this study was Skanska Oy.

Every performance indicator has its strengths and weaknesses.
While selecting performance indicators one should look at variety of measure problems and also focus on intended use of the indicators.
Key figures can be used for example monitoring, planning, diagnosis and control purposes.
Control purpose can be regarded as the main purpose of the indicators.
The usefulness of the indicators suffers for example from different kind of reliability and time related problems.
The study concentrated with more detail to four performance measure indicators.
These indicators referred to schedule deviation, schedule and productivity differentials (production value), task cards and quality index as well as the quality costs.
Indicators were evaluated by the selection criteria, literature and with own reasoning basis.
In addition the meters were analysed and given feedback trough a workshop.

The study was based largely on the literature and the empirical part was narrow.
As a result it can be said that productivity measurement is important when the aim is to continuously and systematically improve productivity.
Productivity should be monitored in several different areas and with different indicators.
Different measurements can be grouped together for example with productivity matrix which can be used to create one key figure to describe the productivity.
Quality and schedule management are just two areas of the building process but they have a significant impact on productivity.
In the end, companies need to weigh the benefits versus trouble with the different indicators to find suitable indicators to support its operations.
As a solution, the target company was advised to construct productivity measurement practices around their QPR system and implement quality costs and production value measurements.
The target company continues to develop performance measure Indicators with the help of this study.
Abstract (fin): Tuottavuus on tärkeä indikaattori sekä yritys- että kansantaloustasolla ja sillä on suora yhteys kannattavuuteen.
Tuottavuudella tarkoitetaan perinteisesti tuotoksen ja panoksen välistä suhdetta, jota kehittämällä parannetaan myös tuottavuutta.
Tuottavuuden kehittämistä, paatoksentekoa ja ohjaustoimintaa voidaan tukea tuottavuusmittauksella.
Rakennusalan monimuotoisuus ja ainutlaatuisuus tekevät kuitenkin tuottavuuden mittaamisesta haastavaa.
Tämän takia tuottavuutta on hyvä lähestyä sitä ilmentävillä suorituskykymittareilla.

Diplomityön aiheena oli tuottavuuden epäsuora mittaaminen laatu- ja aikataulutekijöillä.
Tutkimuksen tavoitteena oli täsmentää tuottavuuden määritelmää rakennusalalla, selvittää aikatauluja laatutekijöiden vaikutusta tuottavuuteen sekä määrittää ja arvioida suorituskykymittarit aikataulu- ja laatutekijöille.
Lisäksi tavoitteena oli määrittää valintakriteerit suorituskykyä mittaaville tunnusluvuille.
Tutkimuksen kohdeyrityksenä toimi Skanska Oy.

Suorituskykyä mittaavilla tunnusluvuilla on aina omat vahvuudet ja heikkoudet.
Tunnuslukujen valinnassa tulee tarkastella erilaisia ongelmia ja käyttötarkoituksia.
Tunnuslukuja voidaan käyttää esimerkiksi seuranta-, suunnittelu-, diagnoosi- ja ohjaustarkoituksessa, jota voidaan pitää myös tunnuslukujen päätarkoituksena.
Tunnuslukujen hyödyllisyys karsii esimerkiksi erilaisten luotettavuus- ja aikaongelmien takia.
Tutkimuksessa käytiin tarkemmin läpi neljä suorituskykymittaria.
Nämä mittarit koskivat aikataulun kokonaispoikkeamaa, aikatauluja tuottavuuseroja (tuotannonarvomenetelmä), tehtäväkortteja ja laatuindeksiä sekä laatukustannuksia.
Mittareita arvioitiin tunnuslukujen valintakriteerien, kirjallisuuden ja oman pohdiskelun pohjalta.
Lisäksi mittareille haettiin palautetta ja kehitysehdotuksia työpajatestauksella.

Tutkimus pohjautui pitkälti kirjallisuuteen ja empiirinen osuus jäi kapeaksi.
Tutkimuksen tuloksena voidaan kuitenkin todeta tuottavuusmittauksen olevan tärkeää, kun tavoitteena on tuottavuuden aktiivinen parantaminen.
Tuottavuutta pitää seurata usealla eri osa-alueella ja tunnusluvulla.
Nämä tunnusluvut voidaan koota yhteen esimerkiksi tuottavuusmatriisissa ja saada nain yksi luku kuvaamaan tuottavuutta.
Laatu- ja aikatauluhallinta ovat vain kaksi rakennusprosessin osa-aluetta, mutta niillä on merkittävä vaikutus tuottavuuteen.
Yritysten tulee loppupeleissä itse punnita eri mittareiden hyötyjä suhteessa niiden vaivaan ja löytää sopivat mittarit tukemaan toimintaansa.
Ratkaisuehdotuksena kohdeyritystä kehotettiin kehittama8n tuloskorttinsa ympärille tuottavuusmittareita ja ottamaan käyttöön sekä tuotannonarvomenetelmän että laatukustannusseurannan.
Mittareiden kehitys jatkuu tämän tutkimuksen pohjalta kohdeyrityksessä.