Author: | Glass, C. |
Title: | Feasibility of scheduling lot sizes of three products on one machine |
Journal: | Management Science
1992 : OCT, VOL. 38:10, p.1482-1494 |
Index terms: | LOT-SIZE MODEL SCHEDULING FEASIBILITY STUDIES INTEGER PROGRAMMING |
Language: | eng |
Abstract: | The Economic Lot Scheduling Problem is to find a feasible schedule that allows cyclic production of several products on a single facility so as to minimize holding and set-up costs. The case is considered when three products are required to be produced in a given fixed lot size and at regular intervals. A simple test is derived for existence of a feasible schedule and a method is presented for constructing feasible schedules if one exists. The approach is simpler than the mixed integer programming one and enumeration schemes currently proposed in the literature. |