search query: @author Tiwari, A. / total: 3
reference: 3 / 3
« previous | next »
Author:Pillai, A.
Tiwari, A.
Title:Enhanced PERT for programme analysis, control and evaluation: PACE
Journal:International Journal of Project Management
1995 : FEB, VOL. 13:1, p. 39-44
Index terms:CONTROL
PERT
PLANNING
Language:eng
Abstract:In PERT, activities are not assigned a priority ranking. The criticality of an activity is, by and large, assessed if it is on the critical path. Further, under PERT, the latent complexities and uncertainties of an activity remain covert. Particularly in high-technology projects, the project-management situation often requires the setting of clear and credible objectives and the formation of viable alternatives in case of any delay in the completion of an activity.