Author:Raz, T.
Marshall, B.
Title:Effect of resource constraints on float calculations in project networks
Journal:International Journal of Project Management
1996 : OCT, VOL. 14:4, p. 241-248
Index terms:PROJECT MANAGEMENT
NETWORKS
ECONOMICS
Language:eng
Abstract:The authors show how the standard method for calculating total float and free float in project schedules might produce misleading results when activities require common resources that are available in limited quantities. The authors propose new float definitions that retain the original meaning while accounting for the effect of resource availability on the schedule. The computational approach presented here is a refinement of the critical path method.
SCIMA record nr: 161177