Author:Etgar, R.
Shtub, A.
LeBlanc, L.
Title:Scheduling projects to maximize net present value - the case of time-dependent, contingent cash flows
Journal:European Journal of Operational Research
1997 : JAN 10, VOL. 96:1, p. 90-96
Index terms:OPERATIONAL RESEARCH
SCHEDULING
CASH FLOW
Language:eng
Abstract:The problem of scheduling activities in a project to maximize its Net Present Value has been solved for the case where net cash flow magnitudes are independent of the time of realization. This paper models a more realistic version of this problem - because of incentive payments and penalties for early and late event occurrences, respectively, and because of changing costs of resources over time, net cash flow magnitudes are dependent on the time of realization.
SCIMA record nr: 178256