search query: @indexterm PERT / total: 49
reference: 9 / 49
« previous | next »
Author:Soroush, H.
Title:The most critical path in a PERT network
Journal:Journal of the Operational Research Society
1994 : MAR, VOL. 45:3, p. 287-300
Index terms:NETWORKS
PROJECT MANAGEMENT
PERT
Language:eng
Abstract:The classical PERT approach uses the path with the largest expected duration as the critical path to estimate the probability of completing a project by a given deadline. However, in general, such a path is not the "most critical" path and does not provide the smallest estimate for the probability of completion time. This paper studies the "most critical path" problem and formulates it as an optimal path problem in a deterministic network with a two-attribute fractional objective function.
SCIMA record nr: 111263