Author: | Demeulemeester, E. Herroelen, W. |
Title: | Modelling setup times, process batches and transfer batches using activity network logic |
Journal: | European Journal of Operational Research
1996 : MAR 8, VOL. 89:2, p. 355-365 |
Index terms: | PROJECT MANAGEMENT SCHEDULING PRODUCTION PLANNING |
Language: | eng |
Abstract: | The objective of this paper is to demonstrate how modelling ideas and solution procedures, borrowed from the field of generalized resource-constrained project scheduling, can be used to formulate and solve several types of production scheduling problems involving sequence-independent setup times as well as process and transfer batches. The computational results provide useful insight in the trade-offs that do exist between the computational effort required and the size of the process and transfer batches used. |