Tekijä: | Heilmann, R. |
Otsikko: | A branch-and-bound procedure for the multi-mode resource-constrained project scheduling problem with minimum and maximum time lags |
Lehti: | European Journal of Operational Research
2003 : JAN 16, VOL. 144:2, p. 348-365 |
Asiasana: | Branch and bound methods Project management Scheduling Time |
Kieli: | eng |
Tiivistelmä: | The paper presents an exact procedure for a general resource-constrained project scheduling problem where multiple modes are available for the performance of the individual activities and minimum as well as maximum time lags between the different activities may be given. The objective is to determine a mode and a start time for each activity such that all constraints are observed and the project duration is minimized. |