Tekijä:Icmeli-Tukel, O.
Rom, W.
Otsikko:Ensuring quality in resource constrained project scheduling
Lehti:European Journal of Operational Research
1997 : DEC, VOL. 103:3, p. 483-496
Asiasana:OPERATIONAL RESEARCH
QUALITY
SCHEDULING
Kieli:eng
Tiivistelmä:This study constitutes an initial effort for modeling and solving resource constrained project scheduling problems with the objective of maximizing quality. Two mixed integer formulations of the problem are introduced. The first formulation assumes integral activity durations and completion times. These assumptions are relaxed in the second formulation. In both formulations the quality of a project is measured by the amount of rework required and the corresponding additional cost incurred. These quality measures are expressed in a common unit of measure and incorporated into the objective function.