Tekijä:Al-Khalil, M. I.
Al-Ghafly, M. A.
Otsikko:Delay in public utility projects in Saudi Arabia
Lehti:International Journal of Project Management
1999 : APR, VOL. 17:2, p. 101-106
Asiasana:PROJECTS
MANAGEMENT
SAUDI ARABIA
Kieli:eng
Tiivistelmä:This study investigates three components of delay in the contruction of water and sewage works in Saudi Arabia: the frequency of delayed projects ; the extent of delay ; the responsibility for delay. A high proportion of projects were subject to delay, the frequency seems to be associated with the contractor classification grade but not with the region where the project is constructed. The extent of delay was severe and it was associated with the original project duration. Project owners and consultants assigned the major responsibility for delay to the constractors while contractors believed that the owner is responsible.