Tekijä:Blackburn, J. D.
Kropp, D. H.
Millen, R. A.
Otsikko:A comparison of strategies to dampen nervousness in MRP systems.
Lehti:Management Science
1986 : APR, VOL. 32:4, p. 413-429
Asiasana:MATERIALS MANAGEMENT
INVENTORY CONTROL
SIMULATION
Kieli:eng
Tiivistelmä:Five different strategies for treating nervousness, or order instability, caused by the interaction of lot-sizing decisions and the planning horizon are proposed and evaluated: (1) Freezing the schedule within the planning horizon, (2) Lot-for-lot after stage 1, (3) Safety stocks, (4) Forecast beyond the planning horizon, and (5) Change cost procedure. A series of simulation experiments was conducted to test the effectiveness of the five strategies on schedule stability and system costs.
SCIMA tietueen numero: 47380