haku: @author Koop, G. J. / yhteensä: 2
viite: 1 / 2
« edellinen | seuraava »
| Tekijä: | Koop, G. J. |
| Otsikko: | Multiple shift workforce lower bounds. |
| Lehti: | Management Science
1988 : OCT, VOL. 34:10, p. 1221-1230 |
| Asiasana: | MANPOWER PLANNING TECHNIQUES NETWORKS |
| Kieli: | eng |
| Tiivistelmä: | The goal of optimal manpower scheduling is to construct schedules which satisfy all of the constraints of a given manpower scheduling problem using no more than the minimum number of workers required by the constraints. Usually this process involves first determining a lower bound on the workforce size and then presenting an algorithm which constructs a feasible schedule using exactly that necessary workforce. Utilized is a network model of the problem to model its multiple shift aspect and provide new lower bounds on workforce size. |