Tekijä:Hung, R.
Otsikko:A multiple-shift workforce scheduling model under the 4-day workweek with weekday and weekend labour demands
Lehti:Journal of the Operational Research Society
1994 : SEP, VOL. 45:9, p. 1088-1092
Asiasana:SCHEDULING
ALLOCATION
MANPOWER PLANNING
Kieli:eng
Tiivistelmä:In this article the author extends previous work on 7-days-a-week, multiple-shift workforce scheduling by considering the 4-day workweek. He seeks to minimize the workforce size subject to satisfying staffing requirements on weekdays and weekends, and workrules relating to shift changes, off-days, and off-weekends. An algorithm is proposed to generate a schedule for a specified horizon. Allocation, manpower planning are discussed.