Tekijä:Harhalakis, G.
Davies, B. J.
Manzoor, T.
Otsikko:Generalized algorithm for the time analysis of summary activities.
Lehti:International Journal of Project Management
1987 : FEB, VOL. 5:1, p. 11-18
Asiasana:PROJECT PLANNING
NETWORK ANALYSIS
ALGORITHMS
Kieli:eng
Tiivistelmä:A review of the time analysis of hammock activities, and their use in network logic drawings to bridge some points as a flexible means to accommodate work of unknown duration in the initial planning stage. An algorithm is proposed that leaves the rest of the network timing and the resulting barcharts uneffected by hammock activities in a computer application. Examples of hammocks placed in various locations of network charts are presented. The study covers the theory and time analysis of hammock activities, examples and a computerized solution. Seven Figures are given.