Otsikko:Project management with time, cost, and quality considerations
Lehti:European Journal of Operational Research
1996 : JAN 20, VOL. 88:2, p. 320-327
Asiasana:OPERATIONAL RESEARCH
PROJECT MANAGEMENT
RESOURCE ALLOCATION
Kieli:eng
Tiivistelmä:In the project management literature, quantitative models were developed for project crashing to determine the appropriate activities for crashing at minimal cost. In this paper the authors suggest that the project quality may be affected by project crashing and develop linear programming models to study the tradeoffs among time, cost and quality. Each of the three models developed optimizes one of these entities by assigning desired bounds on the other two. An illustrative example with a project network consisting of 13 nodes, 14 activities, and 2 dummy activities is provided.