Tekijä:Glass, C.
Otsikko:Feasibility of scheduling lot sizes of three products on one machine
Lehti:Management Science
1992 : OCT, VOL. 38:10, p.1482-1494
Asiasana:LOT-SIZE MODEL
SCHEDULING
FEASIBILITY STUDIES
INTEGER PROGRAMMING
Kieli:eng
Tiivistelmä:The Economic Lot Scheduling Problem is to find a feasible schedule that allows cyclic production of several products on a single facility so as to minimize holding and set-up costs. The case is considered when three products are required to be produced in a given fixed lot size and at regular intervals. A simple test is derived for existence of a feasible schedule and a method is presented for constructing feasible schedules if one exists. The approach is simpler than the mixed integer programming one and enumeration schemes currently proposed in the literature.