haku: @author Berry, W. L. / yhteensä: 7
viite: 4 / 7
Tekijä:Sridharan, V.
Berry, W. L.
Otsikko:Freezing the master production schedule under demand uncertainty.
Lehti:Decision Sciences
1990 : WINTER, VOL. 21:1, p. 97-120
Asiasana:MATERIALS MANAGEMENT
PLANNING
CONTROL
PRODUCTION MANAGEMENT
OPERATIONS MANAGEMENT
SIMULATION
Kieli:eng
Tiivistelmä:Managing the trade-off between achieving a stable master production schedule (MPS) and being responsive to changes in customer requirements is especially difficult if high level customer service is required. As an alternative solution one may freeze an agreed portion of the MPS. The paper examines the impact of adjustments in the design parameters of these methods on two performance measures: MPS lot-sizing costs and stability.
SCIMA tietueen numero: 79007
lisää koriin
SCIMA