Tekijä: | Berends, T. |
Otsikko: | Cost plus incentive fee contracting -- experiences and structuring |
Lehti: | International Journal of Project Management
2000 : JUN, VOL. 18:3, p. 165-172 |
Asiasana: | PROJECT MANAGEMENT OIL INDUSTRY CAPITAL INVESTMENT |
Kieli: | eng |
Tiivistelmä: | In this paper the contractual relationship between owner and Engineering contractor during the development and implementation of capital investment projects is considered. The described Cost Plus Incentive Fee contract type provides a mechanism for allocating project cost risk to the owner, being the party best placed to bear the cost risk consequences and providing a performance incentive for the Engineering Contractor, being the party best placed to manage the cost risk. |