Author:Roimola, Matias
Title:Turvalaitteiden käyttöönottotarkastusprosessin luominen
Developing a process model for commissioning testing of railway signaling systems
Publication type:Master's thesis
Publication year:2011
Pages:[8] + 65 + [19]      Language:   fin
Department/School:Automaatio- ja systeemitekniikan laitos
Main subject:Automaation tietotekniikka   (AS-116)
Supervisor:Koskinen, Kari
Instructor:Lehtola, Juha
OEVS:
Electronic archive copy is available via Aalto Thesis Database.
Instructions

Reading digital theses in the closed network of the Aalto University Harald Herlin Learning Centre

In the closed network of Learning Centre you can read digital and digitized theses not available in the open network.

The Learning Centre contact details and opening hours: https://learningcentre.aalto.fi/en/harald-herlin-learning-centre/

You can read theses on the Learning Centre customer computers, which are available on all floors.

Logging on to the customer computers

  • Aalto University staff members log on to the customer computer using the Aalto username and password.
  • Other customers log on using a shared username and password.

Opening a thesis

  • On the desktop of the customer computers, you will find an icon titled:

    Aalto Thesis Database

  • Click on the icon to search for and open the thesis you are looking for from Aaltodoc database. You can find the thesis file by clicking the link on the OEV or OEVS field.

Reading the thesis

  • You can either print the thesis or read it on the customer computer screen.
  • You cannot save the thesis file on a flash drive or email it.
  • You cannot copy text or images from the file.
  • You cannot edit the file.

Printing the thesis

  • You can print the thesis for your personal study or research use.
  • Aalto University students and staff members may print black-and-white prints on the PrintingPoint devices when using the computer with personal Aalto username and password. Color printing is possible using the printer u90203-psc3, which is located near the customer service. Color printing is subject to a charge to Aalto University students and staff members.
  • Other customers can use the printer u90203-psc3. All printing is subject to a charge to non-University members.
Location:P1 Ark Aalto  5442   | Archive
Keywords:commissioning
testing
validation
interlocking system
process
käyttöönotto
testaus
validointi
turvalaite
asetinlaite
prosessi
Abstract (eng): Railway signalling systems have to be tested carefully before commissioning.
A signalling system consist both trackside equipment, such as turn-outs and signals, and centralised controlling equipment called interlocking systems.
Objective of this thesis is to create general process model for signalling system commissioning tests made by VR Track Ltd.

The thesis consists of three parts.
The first part presents railway signalling systems, signalling system commissioning tests and railway construction business in Finland in general.
The second part presents the legislation and norms that have to be complied in railways.
In the last part, the new process model for signalling system commissioning tests is presented.
The new process model was developed as a result of a research of the railway legislation and norms and investigation of the present commissioning test procedures.

The legislation and norms that have to be complied in railways consists of EU legislation, national legislation, standards and national regulations and requirements.
The strictest norms in practical level are the national regulations given by the Finnish Transport Safety Agency, Trafi, and the requirements given by the Finnish Transport Agency.
Finnish Transport Agency owns and maintains the railway infrastructure in Finland.
From the EU legislation especially the Common Safety Methods (CSM) for risk assessment has to be taken into account.
From the standards especially the safety standards EN50126, EN50128 and EN50129, which concern railway command, control and signalling systems, have to be taken into account.

The commissioning tests are part of the validation process of the signalling systems.
Validation is made in cooperation between equipment supplier, client and person responsible of the testing.
The main task for the person responsible of the testing is typically to validate the system against national regulations and requirements.

As the result of the thesis all parts of the signalling system commissioning test process are defined and all the documentation that has to be produced during the process is specified.
Abstract (fin): Ennen rautatieliikenteen ohjaamiseen käytettävien turvalaitteiden käyttöönottoa on turvalaitteille suoritettava käyttöönottotarkastus.
Turvalaitteilla tarkoitetaan sekä fyysisiä ulkolaitteita kuten opastimia ja vaihteita että ulkolaitteita ohjaavia turvalaitejärjestelmiä kuten asetinlaitteita.
Tämän diplomityön tarkoituksena on muodostaa VR Track Oy:n suorittamiin käyttöönottotarkastuksiin yhteinen prosessimalli.

Työ jakautuu käytännössä kolmeen osaan.
Johdannossa esitellään rautateiden turvalaitteet, turvalaitteiden käyttöönottotarkastus sekä radanrakennusliiketoiminta Suomessa.
Johdannon jälkeen esitellään rautatiealalla vaikuttava lainsäädäntö ja normit.
Lopuksi esitellään rautatiealan normistosta tehtyyn selvitykseen sekä yrityksen sisäisestä toimintamallista tehtyyn tutkimustyöhön perustuva uusi prosessimalli käyttöönottotarkastuksille.

Käyttöönottotarkastuksiin vaikuttavia normeja ovat EU- ja kansallisen tason lainsäädäntö, kansalliset määräykset ja ohjeet sekä standardit.
Eniten käytännön toimintaa koskevat normit ovat Liikenteen turvallisuusvirasto Trafin kansalliset määräykset sekä Suomen ratainfrastruktuuria hallinnoivan Liikenneviraston ohjeet.
EU- lainsäädännön suhteen on huomioitava erityisesti YTM-asetus riskienhallinnasta.
Standardien suhteen on huomioitava erityisesti rautateiden ohjaus-. hallinta- ja merkinantojärjestelmien turvallisuutta käsittelevät standardit EN50126.
EN50128 ja EN50l29.

Turvalaitteiden käyttöönottotarkastus on osa turvalaitejärjestelmän validointiprosessia.
Validointi suoritetaan yhteistyössä laitetoimittajan, tilaajan sekä käyttöönottotarkastajien kesken.
Käyttöönottotarkastajien vastuulle kuuluu tyypillisesti validointi kansallisia määräyksiä ja ohjeita vasten.

Diplomityön tuloksena määritetään käyttöönottotarkastusprosessin osavaiheet sekä tarkastuksista tuotettava dokumentaatio.
ED:2011-08-17