Author:Karvonen, Ville
Title:Putkistosaneerauksen läpimenoajan lyhentäminen 1960- ja 70 -lukujen elementtirakenteisissa asuinkerrostaloissa
Reducing the lead-time of pipe renovation in element apartment houses built at 1960's and 1970's
Publication type:Master's thesis
Publication year:2010
Pages:114 + [13]      Language:   fin
Department/School:Insinööritieteiden ja arkkitehtuurin tiedekunta
Main subject:Talonrakennustekniikka   (Rak-43)
Supervisor:Puttonen, Jari
Instructor:Hytönen, Marko
OEVS:
Electronic archive copy is available via Aalto Thesis Database.
Instructions

Reading digital theses in the closed network of the Aalto University Harald Herlin Learning Centre

In the closed network of Learning Centre you can read digital and digitized theses not available in the open network.

The Learning Centre contact details and opening hours: https://learningcentre.aalto.fi/en/harald-herlin-learning-centre/

You can read theses on the Learning Centre customer computers, which are available on all floors.

Logging on to the customer computers

  • Aalto University staff members log on to the customer computer using the Aalto username and password.
  • Other customers log on using a shared username and password.

Opening a thesis

  • On the desktop of the customer computers, you will find an icon titled:

    Aalto Thesis Database

  • Click on the icon to search for and open the thesis you are looking for from Aaltodoc database. You can find the thesis file by clicking the link on the OEV or OEVS field.

Reading the thesis

  • You can either print the thesis or read it on the customer computer screen.
  • You cannot save the thesis file on a flash drive or email it.
  • You cannot copy text or images from the file.
  • You cannot edit the file.

Printing the thesis

  • You can print the thesis for your personal study or research use.
  • Aalto University students and staff members may print black-and-white prints on the PrintingPoint devices when using the computer with personal Aalto username and password. Color printing is possible using the printer u90203-psc3, which is located near the customer service. Color printing is subject to a charge to Aalto University students and staff members.
  • Other customers can use the printer u90203-psc3. All printing is subject to a charge to non-University members.
Location:P1 Ark Aalto     | Archive
Keywords:pipe renovation
lead-time
apartment house
stage of production
putkiremontti
läpimenoaika
asuinkerrostalo
tuotantovaihe
Abstract (eng): The life cycle of building technology in apartment houses built at 1960s and 1970s is approaching its end.
As a direct result, the number of HVAC-renovations will increase dramatically in the coming years and decades.
To meet this rising demand, the construction industry must develop its HVAC-renovation methods.
One potential target for development is the lead-time of renovation work.
Reduced lead-time brings many different benefits at many locations at the same time.
In a well organized HVAC-renovation, the building residents suffer less anguish; the workers and supervisors could move earlier to other projects and improve the profitability of the renovation.

This research draws knowledge from the prominent literary works of pipe renovation.
This study is also performed by interviewing pipe renovation experts and renovation supervisors.
The main focus of this study is finding the best way to reduce the lead-time of pipe renovations.

Research illustrates how to design production plans for accelerated pipe renovation.
More precisely this study focuses on production scheduling and production supervision.
The pipe contract form in this study is a classic fixed-price contract, which includes renovating the bathrooms and lavatories of buildings, and also renewing the service water and sewer pipes.
Currently, majority of pipe renovations are completed under a contractual agreement where the contractor cannot affect design solutions.

This study primarily concludes that it is possible to significantly reduce the lead-tirne of pipe renovation.
Nowadays the lead-time is at least eight weeks.
However, this requires realistic and well prepared production plans to be made at the very beginning of the project.
Moreover, this study produces two scheduling models for accelerated pipe renovation in a five-story element apartment house.
In the first model the lead-time of the entire pipeline is two weeks and in the second model the lead-time is four weeks.
Abstract (fin): 1960- ja 70 -luvuilla rakennettujen asuinkerrostalojen talotekniikan elinkaaren lähestyessä käyttöikänsä loppua, kasvaa linjasaneerausremonttien volyymi valtavasti lähivuosina ja vuosikymmeninä verrattuna nykytilanteeseen.
Jotta rakennusteollisuus pystyisi vastaamaan tähän lisääntyneeseen kysyntään, on linjasaneerauskorjausten toimintatapoja kehitettävä.
Yhtenä potentiaalisena kehittämiskohteena voidaan pitää korjaustyön läpimenoaikaa.
Läpimenoaikaa lyhentämällä saavutetaan korjaushankkeisiin useita eri hyötyjä samanaikaisesti.
Näin voidaan muun muassa vähentää asukkaiden kokemaa haittaa, vapauttaa työnjohto- ja työntekijäresursseja nopeammin toisiin hankkeisiin sekä parantaa saneerausyritysten kannattavuutta.

Tässä tutkimuksessa on selvitetty pääasiassa kirjallisuustutkimuksen avulla keinoja putkistosaneerausremonttien läpimenoajan lyhentämiseksi.
Lisäksi aiheeseen liittyen on tehty joitakin asiantuntijahaastatteluita.

Tutkimuksessa esitetään tuotantosuunnitelmien laadintaperiaatteet nopeutetun putkistosaneeraushankkeen näkökulmasta.
Erityisesti tuotantosuunnitelmien osalta keskitytään tuotannon aikatauluttamiseen ja tuotantovaiheen ohjauksen tutkimiseen.
Tarkastelussa on käytetty klassista kiinteähintaista urakkamuotoa, jossa uusitaan rakennuksen käyttövesi- ja viemärilinjastot kokonaisuudessaan sekä remontoidaan kosteat tilat.
Lähes kaikki nykypäivän putkistosaneeraukset tehdään sellaisilla urakkamuodoilla, joissa urakoitsija ei voi vaikuttaa suunnitteluratkaisuihin.

Keskeisenä tuloksena tämän tutkimuksen osalta voidaan pitää sitä huomiota, että elementtitalojen putkistosaneerauskorjauksen läpimenoaikaa voidaan lyhentää nykypäivän vähintään kahdeksasta viikosta merkittävästi.
Tämä kuitenkin edellyttää realististen ja hyvätasoisten tuotantosuunnitelmien, erityisesti aikataulujen, laatimista heti tuotantovaiheen alussa.
Tässä työssä esitetään lisäksi kaksi aikataulumallia elementtirakenteisen asuinkerrostalon putkistosaneerauksen tekemiseksi nopeutetusti.
Toisessa mallissa yhden viisikerroksisen linjan läpimenoajaksi muodostui kaksi viikkoa ja toisessa neljä viikkoa.
ED:2010-06-08