Author:Kosonen, Ville Oskari
Title:Development of site operations and supporting resource planning system in crane delivery process
Nostureiden asennusprosessin ja sitä tukevan toiminnanohjausjärjestelmän kehittäminen
Publication type:Master's thesis
Publication year:2012
Pages:(8) + 71      Language:   eng
Department/School:Koneenrakennustekniikan laitos
Main subject:Koneensuunnitteluoppi   (Kon-41)
Supervisor:Kuosmanen, Petri
Instructor:Martikainen, Jouni
OEVS:
Electronic archive copy is available via Aalto Thesis Database.
Instructions

Reading digital theses in the closed network of the Aalto University Harald Herlin Learning Centre

In the closed network of Learning Centre you can read digital and digitized theses not available in the open network.

The Learning Centre contact details and opening hours: https://learningcentre.aalto.fi/en/harald-herlin-learning-centre/

You can read theses on the Learning Centre customer computers, which are available on all floors.

Logging on to the customer computers

  • Aalto University staff members log on to the customer computer using the Aalto username and password.
  • Other customers log on using a shared username and password.

Opening a thesis

  • On the desktop of the customer computers, you will find an icon titled:

    Aalto Thesis Database

  • Click on the icon to search for and open the thesis you are looking for from Aaltodoc database. You can find the thesis file by clicking the link on the OEV or OEVS field.

Reading the thesis

  • You can either print the thesis or read it on the customer computer screen.
  • You cannot save the thesis file on a flash drive or email it.
  • You cannot copy text or images from the file.
  • You cannot edit the file.

Printing the thesis

  • You can print the thesis for your personal study or research use.
  • Aalto University students and staff members may print black-and-white prints on the PrintingPoint devices when using the computer with personal Aalto username and password. Color printing is possible using the printer u90203-psc3, which is located near the customer service. Color printing is subject to a charge to Aalto University students and staff members.
  • Other customers can use the printer u90203-psc3. All printing is subject to a charge to non-University members.
Location:P1 Ark Aalto  6803   | Archive
Keywords:crane
project
erection
delivery
enterprise resource planning system
nosturi
projekti
asennus
toimitus
toiminnanohjausjärjestelmä
Abstract (eng): The last phases of crane delivery process before handover to customer are erection and commission, which together are called as site operations.
From project success point of view these should be planned and executed well, because they affect on project's financial success, customer satisfaction and eventually also whether the agreed handover date can be met or not.

This thesis examined development needs in site operations process especially from delivery project point of view.
Enterprise resource planning system functionalities which match with the development needs and would enhance the project material management were explored.
Also project cost data was analysed to find potential development areas.
In addition, key performance indicators were defined for measuring process performance and enabling comparisons between projects.

The result of the thesis is a process description and supporting resource planning system configuration.
The process enables resource planning and material flow planning and execution, which gives good visibility to project's material flow.
Realization of the good visibility requires that all phases of delivery, meaning also all material movements and subcontracted manufacturing steps, are represented in system, which increases work load of certain users.
Cost data available turned out to be unreliable.
With the new enterprise resource planning system more attention should be paid on posting the site operations related costs to ensure good quality of cost data.
The quality of data can also be affected by reducing the number of cost elements and improving instructions.
Abstract (fin): Nosturitoimitusten viimeiset vaiheet ennen luovutusta asiakkaalle ovat asennus ja käyttöönotto.
Projektin menestyksen kannalta on tärkeää, että ne ovat suunniteltu ja toteutettu hyvin, koska niillä on vaikutusta projektin taloudelliseen tulokseen, asiakastyytyväisyyteen sekä siihen, voidaanko nosturi luovuttaa sovitusti asiakkaalle.

Tässä työssä selvitettiin nosturiasennusten kehityskohteita erityisesti toimitusprojektien kannalta ja etsittiin parannuskohteita käyttöönotettavasta toiminnanohjausjärjestelmästä ja toimitusten materiaalien hallinnasta.
Myös saatavilla ollutta projektien kustannusdataa analysoitiin kehityskohteiden löytämiseksi.
Lisäksi työssä määritettiin mittaristo, jolla asennusprosessin onnistumista voidaan seurata ja vertailla eri projektien välillä.

Työn tuloksena syntyi prosessikuvaus ja sitä tukeva toiminnanohjausjärjestelmän konfiguraatio.
Prosessi mahdollistaa resurssisuunnittelun, sekä materiaalivirtojen suunnittelun ja toteutuksen, mikä antaa hyvän näkyvyyden projektin materiaalivirtoihin.
Näkyvyyden toteutuminen edellyttää kaikkien toimituksen vaiheiden, myös alihankkijoilla tapahtuvan valmistuksen ja materiaalien liikkeiden simuloimista järjestelmässä, mikä osaltaan lisää järjestelmän käyttäjien työn määrää.

Saatavilla ollut kustannusdata osoittautui epäluotettavaksi.
Uuden järjestelmän myötä asennusprosessin aikana syntyvien kustannusten raportoimiseen tulisi kiinnittää aiempaa enemmän huomiota, jotta kustannusdatan laatu olisi nykylista parempi.
Datan laatuun voidaan vaikuttaa myös raportointirakenteen elementtien määrää vähentämällä sekä lisäämällä ohjeistusta.
ED:2012-05-09
INSSI record number: 44452