Author:Andersin, Petteri Antti
Title:Tietomallin käyttö peruskorjaushankkeessa - Case Hakaniemenranta 6
Utilization of building information modeling in a renovation project - Case Hakaniemenranta 6
Publication type:Master's thesis
Publication year:2010
Pages:111 s. + liitt. 14      Language:   fin
Department/School:Rakenne- ja rakennustuotantotekniikan laitos
Main subject:Rakentamistalous   (Rak-63)
Supervisor:Kiiras, Juhani
Instructor:Harmaajärvi, Reijo
OEVS:
Electronic archive copy is available via Aalto Thesis Database.
Instructions

Reading digital theses in the closed network of the Aalto University Harald Herlin Learning Centre

In the closed network of Learning Centre you can read digital and digitized theses not available in the open network.

The Learning Centre contact details and opening hours: https://learningcentre.aalto.fi/en/harald-herlin-learning-centre/

You can read theses on the Learning Centre customer computers, which are available on all floors.

Logging on to the customer computers

  • Aalto University staff members log on to the customer computer using the Aalto username and password.
  • Other customers log on using a shared username and password.

Opening a thesis

  • On the desktop of the customer computers, you will find an icon titled:

    Aalto Thesis Database

  • Click on the icon to search for and open the thesis you are looking for from Aaltodoc database. You can find the thesis file by clicking the link on the OEV or OEVS field.

Reading the thesis

  • You can either print the thesis or read it on the customer computer screen.
  • You cannot save the thesis file on a flash drive or email it.
  • You cannot copy text or images from the file.
  • You cannot edit the file.

Printing the thesis

  • You can print the thesis for your personal study or research use.
  • Aalto University students and staff members may print black-and-white prints on the PrintingPoint devices when using the computer with personal Aalto username and password. Color printing is possible using the printer u90203-psc3, which is located near the customer service. Color printing is subject to a charge to Aalto University students and staff members.
  • Other customers can use the printer u90203-psc3. All printing is subject to a charge to non-University members.
Location:P1 Ark Aalto  1826   | Archive
Keywords:information modeling
building information modeling
BIM
renovation
construction site
project management
tuotemallinnus
tietomallinnus
tietomalli
peruskorjaus
työmaa
projektinjohto
Abstract (eng): This research studies the utilization, challenges and problems of Building Information Model (BIM) in a construction site use.
The case project involved a complete renovation of an eight-storey office building constructed through a project management contract.
The research problem is approached from the point of view of SRV Toimitilat Oy.

All parties of the project were interviewed to document the experiences on working with BIM.
The parties noticed some challenges related to working with the BIM, but they acknowledged that the project was advantageous considering the future projects.
The greatest challenges consisted of a tight planning schedule, writing up an accurate agreement of BIM update procedure and lacking experience with BIM.
It is important to note that the Senate Properties BIM Guidelines 2007 were not yet published when the planning started.
The parties thought that working with BIM will strongly increase in the next few years.

Practical tests were an essential part of the research, including tests on ways the project management contractor can utilize BIM in the construction site.
The tests verified that BIM based quantity calculation is quicker and more accurate than traditional drawing based calculation.
BIM provides up-to-date and accurate quantities, but this requires that the planning and BIM are both up-to-date.
BIM provides distinct three-dimensional material for task planning, visualization and worker briefing.
The tests also compared Solibri Model Checker and Autodesk ADT connected with Tocoman iLink application, and Solibri Model Checker proved remarkably more efficient in construction site use.

The greatest problem in the research was that the BIM revisions did not follow the schedule of the planning progress; they were delayed 1-2 months during the whole project.
The delay was caused by a tight planning schedule, the lack of resources in planning and the planners' lack of experience with BTM.
The project management contractor considered the functionality of Autodesk ADT in construction site BIM work insufficient.

In order to solve the emerged challenges, the research suggests solutions for the future regarding equipment, personnel, and applications and planning.
In addition, the research specifies the working method requirements for successful site utilization of BIM.
The most essential requirements consist of BIM working methods commonly agreed on by planners and the use of IFC format in data transfer.
Abstract (fin): Tutkimuksessa selvitettiin työmaalla tapahtuvan tietomallityöskentelyn toimintaa, sen haasteet ja ongelmat Case- kohteessa, joka oli kahdeksankerroksisen toimistorakennuksen peruskorjaus projektinjohtourakkamuodolla.
Aihetta lähestyttiin projektinjohtourakoitsija SRV Toimitilat Oy:n näkökulmasta.

Tutkimuksen osana kohteen osapuolet haastateltiin tietomallityöskentelyn kokemuksien dokumentoimiseksi.
Vastaajat kokivat kohteen tietomallityöskentelyssä olleen haasteita, mutta pitivät pilottiluonteista hanketta hyödyllisenä tulevien hankkeiden kannalta.
Suurimmiksi haasteiksi osapuolet kokivat kohteen tiukan suunnitteluaikataulun, mallien päivityskäytännön epätarkan märittelyn ja sen, että suunnittelijoilla ei ollut aikaisempaa kokemusta vastaavanlaisesta tietomallityöskentelystä.
Olennaista on, että hankkeen suunnittelun käynnistyessä ei ollut vielä olemassa Senaatin vuonna 2007 julkaisemia tietomallivaatimuksia.
Tietomallintamisen koettiin yleistyvän voimakkaasti lähivuosina.

Oleellisena osana tutkimuksessa olivat käytännön kokeet, joilla testattiin pilottikohteen tietomallin hyödyntämistä projektinjohtourakoitsijan käytössä.
Testit vahvistivat oletuksen, että tietomallipohjainen määrälaskenta on nopeaa ja tarkkaa verrattuna käsin laskentaan.
Tietomallista saadaan ajantasaista ja täsmällistä määrätietoa edellytyksellä, että tietomallia tehdään samassa aikataulussa kuin toteutussuunnittelua.
Tietomallista saadaan helposti havainnollista kolmiulotteista materiaalia työvaiheiden suunnitteluun, visualisointiin ja työntekijäperehdytykseen.
Vertailluista sovelluksista Solibri Model Checker soveltui huomattavasti paremmin työmaan käyttöön kuin Autodesk ADT yhdistettynä Tocoman iLinksovellukseen.

Suurimmaksi ongelmaksi tutkimuksessa koettiin, että pilottikohteen tietomalli oli noin kaksi kuukautta toteutussuunnittelua myöhässä koko hankkeen ajan.
Syynä viiveeseen oli hankkeen tiukka suunnitteluaikataulu, suunnitteluresurssien vähyys ja suunnittelijoiden vähäinen kokemus tietomallintamisesta.
Autodesk ADT:n toimivuus työmaakäytössä koettiin riittämättömäksi.

Tutkimuksessa muodostettiin kehitysehdotukset laitteisiin, henkilöstöön, sovelluksiin ja suunnitteluun liittyvien haasteiden poistamiseksi.
Lisäksi muodostettiin edellytykset, joita noudattamalla työmaan tietomallityöskentely onnistuu suunnitellusti.
Oleellisimmat edellytykset ovat suunnittelijoiden mallinnustyöskentely yhteisesti sovitulla tavalla ja tiedonsiirron tekeminen IFC- muodossa.